SUBJECT
title
Consideration for approval of FY24-ENG-55 World Trade Bridge Building Improvements Project as complete, including all warranty certificates, release of retainage, and final payment in the amount of $136,329.86 to SIMA Contractors, LLC, Laredo, Texas and approval of change order no. 1, a decrease of $118,402.98. The final construction contract amount is $2,726,597.02. Funding is available in the Bridge System Fund.
body
PREVIOUS COUNCIL ACTION
On March 3, 2025, City Council awarded a construction contract to the sole, responsible, responsive bidder Sima Contractors, LLC., Laredo, Texas, in the amount not to exceed $2,845,000.00 for the FY24-ENG-55 World Trade Bridge Building Improvements Project for the total base bid. Construction contract time is 270 working days. Funding is available in the Bridge Construction Projects Fund and 2022 BridgeRevenue Bond.
BACKGROUND
The general scope includes, but not limited to: the general remodeling - renovation of the City of Laredo World Trade Bridge Building
COMMITTEE RECOMMENDATION
N/A
STAFF RECOMMENDATION
recommendation
Approval of this motion.
end

Fiscal Impact
Fiscal Year: 2026
Budgeted Y/N?: Y
Source of Funds: Bridge System Fund
Account #: 553-0000-206-0100
Change Order: Exceeds 25% Y/N: N
FINANCIAL IMPACT:
Funding is available in the Bridge System Fund.
Account # 553-0000-206-0100