Title: Authorizing the City Manager to approve Change Order No. 1, a credit in the amount of ($40,000.00) for eliminating cathodic protection and increase of 67 working days to the contract time due to unforeseen underground and railroad permits from Southern Trenchless Solutions for the 36-inch Water Transmission Main from Jefferson Water Treatment Plant to Zacate Creek. With this change order the contract amount will decrease the contract to a total of $23,440,540.00 and 287 working days. Funding is available in the Waterworks Fund- 2022 Water Revenue Bond.
Attachments: 1. Laredo Jefferson Change Order #1 Signed.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT

title

Authorizing the City Manager to approve Change Order No. 1, a credit in the amount of ($40,000.00) for eliminating cathodic protection and increase of 67 working days to the contract time due to unforeseen underground and railroad permits from Southern Trenchless Solutions for the 36-inch Water Transmission Main from Jefferson Water Treatment Plant to Zacate Creek. With this change order the contract amount will decrease the contract to a total of $23,440,540.00 and 287 working days. Funding is available in the Waterworks Fund- 2022 Water Revenue Bond.

 

body

VIVA LAREDO PLAN ALIGNMENT

Alignment Rating: Moderate

Supporting goal(s)/policy(ies):

Policy 6.5.7 Continue to implement the existing water conservation program

Policy 7.2.4 Increase access to safe water

Summary of alignment:

This agenda item update aligns with Viva Laredo’s Comprehensive Plan goals and policies addressing water quality by replacing aged water lines.

 

 

PREVIOUS COUNCIL ACTION

On March 18, 2024 the City Council approved the construction contract to Southern Trenchless Solutions in the amount of $23,480,540.00 with a contract time of 220 working days for the 36-inch Water Transmission Main from Jefferson Water Treatment Plant to Zacate Creek.

 

BACKGROUND

This change order is for a credit of (440,000.00)

 

Contract

Amount

Working Days

Original Contract

$23,480,540.00

220

Change Order No. 1

($40,000.00)

67

Total

$23,440,450.00

287

 

COMMITTEE RECOMMENDATION

N/A

 

STAFF RECOMMENDATION

recommendation

Approval of Motion

end

Fiscal Impact

 

Fiscal Year:                                                                                                          2025

Budgeted Y/N?:                                                                                    Yes

Source of Funds:                                                                                     2022 Water Revenue Bond

Account #:                                                                                                          557-9879-535-9301

Change Order: Exceeds 25% Y/N:                      No

 

FINANCIAL IMPACT:

Funding is available in the Waterworks Fund- 2022 Water Revenue Bond. Account 557-9879-535-9301. Project ID: WP2204