SUBJECT
title
Authorizing the City Manager to approve final change order #3 in the amount of $17,000.00 to Southern Trenchless Solutions of Weslaco, Texas for 24-inch Water Transmission Main from Loop 20 Airport to Bustamante project. The updated contract is $6,738, 801.50. Funding is available in the Waterworks Fund - 2022 Water Revenue Bond
body
PREVIOUS COUNCIL ACTION
On June 5, 2023 council approved the construction contract to Southern Trenchless Solutions of Weslaco, Texas for the construction of 24-inch Water transmission Main in the amount of $5,773,625.00
On July 22, 2024, City Council approved change order #1 in the amount of $716,865.36.
On April 7, 2025, City Council approved change order #2 in the amount of $231,311.14.
BACKGROUND
It is recommended to proceed with the Construction Material to ensure the completion of the 24-inch Water Transmission Main from Loop 20 Airport to Bustamante project.
Contract Amount Working Days
Original Contract: $5,773,625.00 250
Change Order # 1: $716,865.36 0
Change Order # 2: $231,311.14 50
Change Order # 3: $17,000.00 144
Total: $6,738,801.50 444
VIVA LAREDO PLAN ALIGNMENT
Alignment Rating: Moderate
Supporting goal(s)/policy(ies):
Policy 6.5.7 Continue to implement the existing water conservation program
Policy 7.2.4 Increase access to safe water
Summary of alignment:
This agenda item update aligns with Viva Laredo's Comprehensive Plan goals and policies related to efficient water utilization and sustainable development.
COMMITTEE RECOMMENDATION
None.
STAFF RECOMMENDATION
recommendation
Approve this motion.
end
Fiscal Impact
Fiscal Year: 2026
Budgeted Y/N?: Y
Source of Funds: 2022 Water Rev...