SUBJECT
title
Consideration to ratify and amend the issuance of Purchase Order 430326 to Murphy Pipeline Contractors, in the amount of $1,697,174.12. This amendment is for the additional work needed for the water line replacement program. The updated contract is $15,412,048.26. Funding is available in the Waterworks Fund - 2022 Water Revenue Bond.
body
PREVIOUS COUNCIL ACTION
On May 19, 2025 Council approved the construction contract to Murphy Pipeline Contractors for the waterline replacement program in the amount of $11,314,949.14
On December 01, 2025, City Council approved change order #1 in the amount of $2,399,925.00.
BACKGROUND
Additional work are for the following streets:
Kearney St - 500 LF
N Unitec Dr. - 1,350 LF
RB Group Entrance - 1,500 LF
Ireland St - 1,350 LF
VIVA LAREDO PLAN ALIGNMENT
Alignment Rating: Moderate
Supporting goal(s)/policy(ies):
Policy 6.5.7 Continue to implement the existing water conservation program.
Policy 7.2.4 Increase access to safe water.
Summary of alignment:
This agenda item update aligns with Viva Laredo’s Comprehensive Plan goals and policies related to efficient water utilization and sustainable development.
COMMITTEE RECOMMENDATION
None.
STAFF RECOMMENDATION
recommendation
Approve this motion.
end

Fiscal Impact
Fiscal Year: 2026.
Budgeted Y/N?: Yes.
Source of Funds: 2022 Water Revenue Bond.
Account #: 557-9879-535-9301.
Change Order: Exceeds 25% Y/N: No.
FINANCIAL IMPACT:
Funding is available in the Waterworks Fund - 2022 Water Revenue Bond Account #557-9879-535-9301, Project ID: WP1801