SUBJECT
title
Authorizing City Manager to approve final change order in the amount of $23,918.83, release of retainage, final payment in the amount of $ 82,618.84, and final project acceptance to J.S. Haren, LLC for Jefferson Water Treatment Plant Chlorine Feed Improvements Project. The updated contract amount is $817,918.83. The total number of working days is 170. Funding is available in the Waterworks Fund- 2022 Water Revenue Bond.
body
PREVIOUS COUNCIL ACTION
On June 5, 2023 council approved award of construction contract to J.S. Haren, LLC in the amount of $794,000.00 Jefferson Water Treatment Plant Chlorine Feed Improvements Project.
BACKGROUND
N/A
COMMITTEE RECOMMENDATION
NA
STAFF RECOMMENDATION
recommendation
Approval of motion.
end

Fiscal Impact
Fiscal Year: 2024
Budgeted Y/N?: Y
Source of Funds: 2022 Water Revenue Bond
Account #: 557-9879-535-9301
Change Order: Exceeds 25% Y/N: N
FINANCIAL IMPACT:
Funding is available in the 2022 Water Revenue Bond. Account 557-9879-535-9301 Project WP2306