SUBJECT
title
Authorizing the City Manager to award Contract FY25-069 to the lowest responsive bidder, Soliz Paving, Inc. of Laredo, Texas, in the amount of $985,421.00 for the provision of all necessary machinery, equipment, labor, supervision, and other services and appurtenances required for the elimination of the Uniroyal Lift Station. The scope of work the installation of 1,417 LF of 8” PVC pipe, five fiberglass manholes, street access improvements and road restoration. Funding for this project is available in the Sewer System Fund- 2019 Sewer Revenue Bond.
body
VIVA LAREDO PLAN ALIGNMENT
Alignment Rating:
Supporting goal(s)/policy(ies):
Summary of alignment:
PREVIOUS COUNCIL ACTION
None
BACKGROUND
The Uniroyal Lift Station, constructed in 1992, was made obsolete by the installation of a new nearby gravity sewer line, allowing for its decommissioning. Two companies submitted bids for this project. The pricing summary is as follows
Soliz Paving Inc. $ 985,421.00
Sal Construction Management $1,110,258.00
Bid tabulation is attached
COMMITTEE RECOMMENDATION
None
STAFF RECOMMENDATION
recommendation
It is recommended that this action is approved
end

Fiscal Impact
Fiscal Year: 2025
Budgeted Y/N?: N
Source of Funds: 2019 Sewer Revenue Bond
Account #: 559-9875-535-9301
Change Order: Exceeds 25% Y/N: N
FINANCIAL IMPACT:
Funding is available in the Sewer System Fund- 2019 Sewer Revenue Bond
Account number 559-9875-535-9301
Project Number SW2401