Title: Consideration for approval of FY24-ENG-72 Rebid Inner City Park Pool Fabric Shade Structure Replacement Project as complete, including all warranty certificates, release of retainage, and final payment in the amount of $41,115.00 to ABBA Construction, LLC, Laredo, Texas and approval of change order no. 1, a decrease of $5,850.00. The final construction contract amount is $411,150.00. Funding is available in the 2022 and 2023 Certificate of Obligation Bonds.
Attachments: 1. Change Order #1, 2. Final Pay App - FY24-ENG-72
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT

title

Consideration for approval of FY24-ENG-72 Rebid Inner City Park Pool Fabric Shade Structure Replacement Project as complete, including all warranty certificates, release of retainage, and final payment in the amount of $41,115.00 to ABBA Construction, LLC, Laredo, Texas and approval of change order no. 1, a decrease of $5,850.00. The final construction contract amount is $411,150.00. Funding is available in the 2022 and 2023 Certificate of Obligation Bonds.

 

body

PREVIOUS COUNCIL ACTION

On December 2, 2024, City Council awarded a construction contract to the sole, responsible, responsive bidder Abba Construction, LLC., Laredo, Texas, in the amount not to exceed $417,000.00 for the FY24-ENG-72 Rebid Inner City Park Pool Fabric Shade Structure Replacement Project for the total base bid including a $10,000.00 contingency allowance. Funding is available in the 2023 Certificate of Obligation Bond.

 

BACKGROUND

This project consists of installing a fabricated PVC mesh roof type, and replacing all of its anchorage components including but not limited to: structural support cables, end fittings, clamps/turnbuckles, and structural embedded plates in accordance with the latest adopted International Building Code requirements, and a minimum of one (1) year workmanship warranty.

 

COMMITTEE RECOMMENDATION

N/A

 

STAFF RECOMMENDATION

recommendation

Approval of this motion.

end

Fiscal Impact

 

Fiscal Year:                                                                                                          2026

Budgeted Y/N?:                                                                                    Y

Source of Funds:                                                                                     2023 CO Bond

Account #:                                                                                                          Various

Change Order: Exceeds 25% Y/N:                      N

 

FINANCIAL IMPACT:

Funding is available in the 2023 Certificate of Obligation Bond.
Account                        Project              Retainage amount
475-0000-206-0100         PA2402               $9,685.40