Consideration for approval of the Laredo International Airport construction of Taxiways H1 and H2 and a portion of Taxiway Alpha as complete, release of retainage and approval of final payment in the amount of $455,379.64 to REIM Construction, Inc., Mission, Texas. Funding is available in the Airport Construction Fund FAA Grant 100.
body
PREVIOUS COUNCIL ACTION
On April 7, 2025 City Council approved change order no. 2 a decrease of $418,738.66 to the Construction contract with REIM Construction, In., Mission, Texas for the Laredo International Airport Construction of Taxiways H1 and H2 and Reconstruction of a portion of Taxiway A. Change Order 2 consists of deductions for quantities in place, modifications for sign installed on Taxiways H2 and H2 per FAA inspector comments, restriping for Taxiways D and H, and reduction for P-501 concrete panel repairs.
On August 21, 2023. City Council approved change order no. 1 a decrease of $447,503.40 to the Constuction contract with REIM Construction, Inc., Mission, Texas,
for the Laredo International Airport Construction of Taxiways H1 and H2 and Reconstruction of a portion of Taxiway A. Change Order 1 consists of the deletion of 1,220 SY of Taxiway A reconstruction, located south of Taxiway D, due to a reduction in bid item quantities from Bid Alternate 1. The affected bid items include pavement removal, new concrete a pavement section, erosion control, and pavement markings. Current construction contract amount with this change order no. is $9,181,726.60.
On November 17, 2022, City Council awarded a construction contract to the lowest responsible responsive bidder REIM Construction, Inc., Mission, Texas, in the amount of $9,629,230.00 for the Laredo International Airport Construction of Taxiways H1 and H2 and Reconstruction of a portion of Taxiway A and authorizing the City Manager to execute all related contract documents contingent upon receipt and approval of Insurance and Bond documents.