Title: Authorizing City Manager to negotiate and execute a supply and service contract with A-1 Scale Service, Inc., San Antonio, Texas in the total amount of $139,929 for the Solid Waste Department scale house. The scale house scales need a new VKR211 Upgrade Kit. Funding is available in the Solid Waste Fund.
Attachments: 1. VKR211 Upgrade Kit (7), 2. Sole Source
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT

title

Authorizing City Manager to negotiate and execute a supply and service contract with A-1 Scale Service, Inc., San Antonio, Texas in the total amount of $139,929 for the Solid Waste Department scale house. The scale house scales need a new VKR211 Upgrade Kit. Funding is available in the Solid Waste Fund.

 

body

PREVIOUS COUNCIL ACTION

N/A

 

BACKGROUND

A-1 Scale has been keeping our scales in compliance with Texas of Agriculture for the past 20 years, we have never had any issues or problems with them.

A-1 Scale Services:
VKR211 upgrade kit for MTX Scale
Full Coverage 10 Year Guarantee includes lightning protection
Mettler Toledo Model: VKR211 upgrade kit, (10) 50t PDX power cells
(10) upper and (10) lower receivers cups, heavy-duty cables
PDX homerun cable, from scale to scale house
POWERCELL PDX Channel IND780
Grading 40' x 20"
Total Scale Equipment $57,829

Jack and block scale up, remove (20) old upper and lower receiver cups, install (20) new upper and lower receiver cups, a welder would be on site to weld bolts to upper receiver cups, to remove receiver cups, run PDX power cells and cables, install new PDX channel cards setup and calibrate 2 scale to IND780.

Total Installation $29,400

Cut both sidewalks on each side of the scale house up to 18"w x 40'L x 15"D, need to cut side rails to remove sidewalks, weld back together when completed, rent a backhoe with a hammer to break sidewalk, clean up sidewalks on both ends, build three (3)
piers for rails.
Total Construction $52,700

Total Project Price is $139,929

 

COMMITTEE RECOMMENDATION

None

 

STAFF RECOMMENDATION

recommendation

Staff recommends that this contract be awarded.

end

Fiscal Impact

 

Fiscal Year:                                                                                                          2025

Budgeted Y/N?:                                                                                    Y

Source of Funds:                                                                                     Solid Waste

Account #:                                                                                                          556-2560-535-9001

Change Order: Exceeds 25% Y/N:                      

 

FINANCIAL IMPACT: