SUBJECT
title
Authorizing City Manager for final project acceptance of the construction of the City of Laredo 24-Inch WTR PRV Station inside Airport, including all warranty certificates, release of retainage, and final payment in the amount of $24,290.91 to Southern Trenchless Solutions. The final construction contract amount of $242,909.10 and final contract time of 62 working days. Funding is available in the Water System Fund-2022 Water Revenue Bond.
body
VIVA LAREDO PLAN ALIGNMENT
Alignment Rating: Moderate
Supporting goal(s)/policy(ies):
Policy 6.5.7 Continue to implement the existing water conservation program
Policy 7.2.4 Increase access to safe water
Summary of alignment:
This agenda item update aligns with Viva Laredo’s Comprehensive Plan goals and policies related to efficient water utilization and sustainable development.
PREVIOUS COUNCIL ACTION
On December 2, 2024 council approved the construction contract to Southern Trenchless Solutions of City of Weslaco, Texas in the amount of $242,909.10 with a contract time of 180 working days to execute the contract utilizing Buy Board Cooperative Purchasing Program.
BACKGROUND
A Pressure Reducing Valve (PRV) to be installed inside the Airport for the 24-inch Water Transmission Line.
|
Contract |
Amount |
Working Days |
|
Original Contract: |
$242,909.10 |
180 |
|
Total: |
$242,909.10 |
180 |
COMMITTEE RECOMMENDATION
None
STAFF RECOMMENDATION
recommendation
Approve this motion.
end

Fiscal Impact
Fiscal Year: 2026
Budgeted Y/N?: Y
Source of Funds: 2022 Water Revenue Bond
Account #: 557-9877-535-9301
Change Order: Exceeds 25% Y/N: N
FINANCIAL IMPACT:
Funding is available in the 2022 Water Revenue Bond Account #557-9877-535-9301, Project ID: WP2201