SUBJECT
title
Consideration for approval of FY24-ENG-47 Springfield Avenue Extension Phase 4 Project as complete, including all warranty certificates, release of retainage, and final payment in the amount of $36,851.95 to ALC Construction, Inc., Laredo, Texas and approval of change order no. 1 in a decrease of $28,260.00. The final construction contract amount is $737,039.00. Funding is available in the Capital Grants Fund.
body
VIVA LAREDO PLAN ALIGNMENT
Alignment Rating:
Supporting goal(s)/policy(ies):
Summary of alignment:
PREVIOUS COUNCIL ACTION
On February 18, 2025, city council approved to award a construction contract to the lowest, responsible, responsive bidder ALC Construction, LLC., Laredo, Texas, in the amount not to exceed $765,299.00 for the FY24-ENG-47 Springfield Avenue Extension Phase 4 Project for the total base bid, including a $40,000 contingency allowance. Funding is available in the Capital Grants Fund and 2020A Water Revenue Bond.
BACKGROUND
The project consists of Constructing approximately 2400 SY of roadway pavement, 11,700 SF of sidewalks, 600 LF of 12” PVC Water Main, with related ramps, striping, landscape, appurtenances, and incidentals. Construction contract time will be 90 working days.
COMMITTEE RECOMMENDATION
N/A
STAFF RECOMMENDATION
recommendation
Approval of this motion.
end

Fiscal Impact
Fiscal Year: 2025
Budgeted Y/N?: Y
Source of Funds: Capital Grants Fund
Account #: 458-2663-525-9301
Change Order: Exceeds 25% Y/N: N
FINANCIAL IMPACT:
Funding is available in the Capital Grants Fund. Account #458-2663-525-9301, Project TP2403