File #: 25-P&Z-39    Version: 1
Type: Master Plan Consideration Status: Agenda Ready
File created: 3/24/2025 In control: Planning & Zoning Commission
On agenda: 4/3/2025 Final action:
Title: Review of the revision to the Embarcadero Southeast Quadrant Masterplan. The intent is commercial and industrial. The purpose of this revision is to reconfigure lots in Phase 9 and Phase 11. PL-099-2025 District VII - Cm. Vanessa Perez
Attachments: 1. Aerial Location Map, 2. Embarcadero SEQ Masterplan - Current Masterplan (Approved by P&Z on 08-01-2024), 3. Embarcadero SEQ Masterplan - Revised Masterplan Submitted
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT
title
Review of the revision to the Embarcadero Southeast Quadrant Masterplan. The intent is commercial and industrial. The purpose of this revision is to reconfigure lots in Phase 9 and Phase 11.

PL-099-2025
District VII - Cm. Vanessa Perez

body
PREVIOUS COUNCIL ACTION
N/A

BACKGROUND
APPLICANT: Farias Development, Ltd.
ENGINEER: Camacho-Hernandez & Associates, LLC

SITE: This 235.11-acre tract of land is located southeast quadrant of FM 1472 (Mines Road) and Bob Bullock Loop. The zoning for this development is B-4 (Highway Commercial District) and M-1 (Light Manufacturing District). This tract is located in District VII - Cm. Vanessa Perez.

COMMITTEE RECOMMENDATION
N/A

STAFF RECOMMENDATION
recommendation
APPROVE SUBJECT TO THE FOLLOWING COMMENTS:

Planning:
1. Add a phase boundary line between Phase 4 and Phase 5.
2. Clarify the phase in which the 5.63-acre segment of Fasken Boulevard will be constructed on the masterplan.
3. Submit a masterplan revision to the City of Laredo Building Department GIS referenced CAD file (sec. 2-3.2 (a) 4 - Subdivision Ordinance).
4. Access to FM 1472, Bob Bullock Loop, and Interstate Highway 35 is subject to the review and approval by the Texas Department of Transportation (TX-DOT).
5. Comply with the vegetative buffering requirements as per first-and third-order stream impacts a portion of this tract (sec. 24-27 - Laredo Land Development Code).
6. Identify all easements.
7. All improvements as per the Subdivision Ordinance.

Engineering: No comments submitted
Fire: No comments submitted.
Environmental: No comments submitted.
Water & Utilities: No comments submitted.
Traffic Safety: No comments submitted.
Parks & Leisure: No comments submitted.
WEBB County App: No comments submitted.
AEP Engineers: No comments submitted.
U.I.S.D.: No comments submitted.
L.I.S.D.: No comments submitted.
AT&T: No comments submitted.


NOTICE TO THE DEVELOPER:

Planning:
1. Only the utility easements within the p...