Title: Consideration to award a construction contract to the lowest responsible, responsive bidder Alcan Contracting, LLC, Laredo, Texas in the amount not to exceed $463,154.60 for FY24-ENG-81 Santa Fe Park Trail Project for the total base bid. Construction contract time is 120 working days. Funding is available in the Park Capital Grants Fund and 2025 Certificate of Obligation Bond. 1. Alcan Contracting, LLC, Laredo, Texas Total Base Bid: $463,154.60 2. 21 Construction Services, LLC, Laredo, Texas Total Base Bid: $473,704.00 3. Cid Group Inc., Laredo, Texas Total Base Bid: $550,127.61 4. ALC Construction Co., Inc., Laredo, Texas Total Base Bid: $560,404.00 5. ANAHUAC Infrastructure, Brownsville, Texas Total Base Bid: $624,912.76 6. Zertuche Construction Texas LLC, Laredo, Texas Total Base Bid: $753,333.00 Refer to attached letter of recommendation.
Attachments: 1. FY24-ENG-81 Award Recommendation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
/
SUBJECT
title
Consideration to award a construction contract to the lowest responsible, responsive bidder Alcan Contracting, LLC, Laredo, Texas in the amount not to exceed $463,154.60 for FY24-ENG-81 Santa Fe Park Trail Project for the total base bid. Construction contract time is 120 working days. Funding is available in the Park Capital Grants Fund and 2025 Certificate of Obligation Bond.

1. Alcan Contracting, LLC, Laredo, Texas
Total Base Bid: $463,154.60
2. 21 Construction Services, LLC, Laredo, Texas
Total Base Bid: $473,704.00
3. Cid Group Inc., Laredo, Texas
Total Base Bid: $550,127.61
4. ALC Construction Co., Inc., Laredo, Texas
Total Base Bid: $560,404.00
5. ANAHUAC Infrastructure, Brownsville, Texas
Total Base Bid: $624,912.76
6. Zertuche Construction Texas LLC, Laredo, Texas
Total Base Bid: $753,333.00

Refer to attached letter of recommendation.

body
PREVIOUS COUNCIL ACTION
N/A

BACKGROUND
This project consists of constructing approximately 3372 LF of 10' wide concrete trail, including rehabilitation/stabilization of existing concrete channel, pedestrian railing, and subsidiary work.
Construction contract time for the project is one hundred and twenty (120) Working Days.

A total of six (6) bids were received at the City Secretary’s office on Monday, September 14, 2026 at 4:00 P.M. which were publicly opened, read and taken advertisement on Tuesday, September 15, 2026 at 10:00 A.M.


Total Base Bid
21 Construction Services, LLC $473,704.00
ALC Construction Co., Inc. $560,404.00

Alcan Contracting, LLC
$463,154.60

ANAHUAC Infrastructure
$624,912.76

Cid Group Inc.
$550,127.61

Zertuche Construction Texas LLC
$753,333.00


Refer to attached letter of recommendation.

COMMITTEE RECOMMENDATION
N/A

STAFF RECOMMENDATION
recommendation
Approval of this motion.
end
/
Fiscal Impact

Fiscal Year: 2026
Budgeted Y/N?: Y
Source of Funds: Various
Account #: Various
Change Order: Exceeds 25% Y/N: N/...