Skip to main content

File #: 25-173    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 1/14/2025 In control: City Council
On agenda: 2/18/2025 Final action:
Title: Consideration for approval of the Laredo International Airport Taxiways G1 and G2 construction as complete, release of retainage and approval of final payment in the amount of $109,335.30 to REIM Construction, Inc., Mission, Texas. Current construction contract amount is $7,919,033.75. Funding is available in the Airport Construction Fund.
Attachments: 1. Taxiways G1 and G2_Engineers completion letter 11-6-2024, 2. TWY G1 & G2 Engineers FULL release of retainage
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT
title
Consideration for approval of the Laredo International Airport Taxiways G1 and G2 construction as complete, release of retainage and approval of final payment in the amount of $109,335.30 to REIM Construction, Inc., Mission, Texas. Current construction contract amount is $7,919,033.75. Funding is available in the Airport Construction Fund.

body
PREVIOUS COUNCIL ACTION
On October 28, 2024, City Council approved a change order No. 3 for the Laredo International Airport Taxiways G1 and G2 Construction to REIM Construction Inc., Mission, Texas for a decrease in the amount of $50,046.29. The revised contract amount, including this change order, is $7,919,033.76. Funding is available in the Airport Construction Fund FAA Grant 95.

On June 24, 2024, City Council approved the Laredo International Airport Taxiways G1 and G2 construction as substantially complete and release of a partial retainage payment of the items that are one hundred percent completed and accepted in the amount of $239,072.40 to REIM Construction, Inc., Mission, Texas. Current construction contract amount is $7,969,080.04.

On August 16, 2021, City Council approved to award a construction contract to the lowest responsible bidder REIM Construction, Inc. Mission, Texas, in the amount of $8,219,272.45 for the Laredo International Airport Taxiways G1 and G2 construction with a construction time of three hundred seventy-five (375) calendar days; and authorizing the City Manager to execute all related contract documents contingent upon receipt and approval of insurance and bond documents. After a notice to proceed is issued, the estimated completion date for the project is September 2022. Funding is available in the Airport Construction Fund Grant No. 95. This item is contingent on approval of Ordinance 2021-O-154.

BACKGROUND
The project consists of:

The construction of two new taxiways, Taxiway G1 and Taxiway G2, between Taxiway G and Runway 18R-36L, and the decommissioning of Taxiway ...