SUBJECT
title
Authorizing the City Manager to ratify a purchase order in the amount of $343,000.00 to Rain for Rent for an emergency contract. This contract was necessary to install a 36-inch wastewater bypass line in order to prevent raw sewage from discharging into the Rio Grande River and to maintain sewer flow to the South Laredo Wastewater Treatment Plant. Funding for this contract is available through the Sewer System Fund - 2022 Sewer Revenue Bond.
body
VIVA LAREDO PLAN ALIGNMENT
Alignment Rating: N/A
Supporting goal(s)/policy(ies): N/A
Summary of alignment: N/A
PREVIOUS COUNCIL ACTION
N/A
BACKGROUND
On September 26, 2025, the City experienced a major break on the existing 36-inch wastewater line. As this line serves as one of the primary collectors to the South Laredo Wastewater Treatment Plant, it was imperative to immediately provide a bypass to prevent raw sewage from entering the Rio Grande River and causing contamination. Given that Rain for Rent had the necessary equipment readily available and was capable of responding without delay, the City engaged the company to perform the emergency bypass.
COMMITTEE RECOMMENDATION
None
STAFF RECOMMENDATION
recommendation
Approval for Motion
end

Fiscal Impact
Fiscal Year: 2025
Budgeted Y/N?: Y
Source of Funds: 2024 Sewer Revenue Bond
Account #: 559-9877-535-9301
Change Order: Exceeds 25% Y/N: N
FINANCIAL IMPACT:
Funding is available in the 2024 Water Revenue Fund Acct. No.559-9877-535- 9301 Project ID: SW2517