SUBJECT
title
Consideration for approval of FY24-ENG-09 Maria Elida Benavides Restroom and Sidewalk ADA Project as complete, including all warranty certificates, release of retainage, and final payment in the amount of $17,830.00 to ALC Construction, Inc., Laredo, Texas and approval of change order no. 1 to balance final quantities. The final construction contract amount is $101,800.00. Funding is available in the 2022 Certificate of Obligations Fund- District 2 Priority Funds and the Community Development Fund.
body
PREVIOUS COUNCIL ACTION
On August 5, 2024, city council approved to award a construction contract to the lowest, responsible, responsive bidder ALC Construction, LLC., Laredo, Texas, in the amount not to exceed $101,800.00 for the FY24-ENG-09 Maria Elida Benavides Restroom and Sidewalk ADA Restoration District 2 Project for the total base bid, additive alternate #1, and including a $5,000.00 contingency allowance. Funding is available in the Community Development Fund- 2021 and 2022 CDBG Grant Years and 2022 Certificate of Obligations Fund- District 2 Priority Funds.
BACKGROUND
This project consists of reconstructing a concrete sidewalk to make it ADA compliant as well as restroom restorations that include the following: 500 SF. of concrete removal and concrete sidewalk, ADA ramps, door widening, minisplit installation, wall painting, counter replacement, tile installation. Construction contract time for the project is (60) working days.
COMMITTEE RECOMMENDATION
N/A
STAFF RECOMMENDATION
recommendation
Approval of this motion.
end
Fiscal Impact
Fiscal Year: 2025
Budgeted Y/N?: Y
Source of Funds: District Priority Funds and CDBG
Account #: Various
Change Order: Exceeds 25% Y/N: N/A
FINANCIAL IMPACT:
Funding is available in the 2022 Certificate of Obligations Fund- District 2 Priority Funds.
Account 475-3118-555-9301; project D22216 $8,500.00.
Retainage Accts: 475-0000-206-0100 $4,812.20 and 211-0000-206-0100 $4,517.80
...