File #: 25-1439    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 8/1/2025 In control: City Council
On agenda: 8/18/2025 Final action:
Title: Authorizing the City Manager to approve the final payment in the amount of $22,000.00 and to release the retainage of $30,300.00 for a total amount of $52,300.00 to SAL Construction and Management LLC, for the Manhole Repair located in IH35, and to accept the project as complete. Funding for this payment is available from the Sewer System Fund- 2019 Sewer System Revenue Bond
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT

title

Authorizing the City Manager to approve the final payment in the amount of $22,000.00 and to release the retainage of $30,300.00 for a total amount of $52,300.00 to SAL Construction and Management LLC, for the Manhole Repair located in IH35, and to accept the project as complete. Funding for this payment is available from the Sewer System Fund- 2019 Sewer System Revenue Bond

 

body

 

 

PREVIOUS COUNCIL ACTION

On July 21, 2025 City Council approved the emergency PO to SAL Construction and Management LLC in the amount of $325,000.00 for the repairs of a collapsed manhole.

 

BACKGROUND

The project has been completed in accordance with the repair specifications and is ready for final acceptance

 

COMMITTEE RECOMMENDATION

None

 

STAFF RECOMMENDATION

recommendation

Approval of Motion

end

Fiscal Impact

 

Fiscal Year:                                                                                                          2025

Budgeted Y/N?:                                                                                    Y

Source of Funds:                                                                                     2019 Sewer Revenue Bond

Account #:                                                                                                          559-9875-535-9301

Change Order: Exceeds 25% Y/N:                      N

 

FINANCIAL IMPACT:

Sewer System Fund- 2019 Sewer Revenue Bond
Account 559-9875-535-9301
Project Number SW1801.

Retainage account 559-000-206-0100