Skip to main content

File #: 26-506    Version: 1
Type: Consent Agenda Status: Passed
File created: 3/2/2026 In control: City Council
On agenda: 3/16/2026 Final action: 3/16/2026
Title: Consideration to award service contract RFB2026-045 to the lowest responsive/responsible bidder Murphy Pipeline Contractors, Sunrise, Florida, in the amount of $11,153,320.00 for the water line installation by pipe bursting and/or horizontal directional drilling (HDPE) for the Utilities Department. Estimated time for completion of this project is two hundred twenty (220) working days. Funding is available in the Waterworks Fund - 2024 Water Revenue Bond
Attachments: 1. 26-506 Eng RFB 2026-045 Sal Const Attch 4, 2. 26-506 Eng RFB 2026-045 Renoworks Attch 3, 3. 26-506 Eng RFB 2026-045 Murphy Pipeline Attch 2, 4. 26-506 Eng Bid Tabulation - RFB2029-045 Pipe Bursting Project Phase 2

SUBJECT

title

Consideration to award service contract RFB2026-045 to the lowest responsive/responsible bidder Murphy Pipeline Contractors, Sunrise, Florida, in the amount of $11,153,320.00 for the water line installation by pipe bursting and/or horizontal directional drilling (HDPE) for the Utilities Department. Estimated time for completion of this project is two hundred twenty (220) working days.  Funding is available in the Waterworks Fund - 2024 Water Revenue Bond

 

body

 

PREVIOUS COUNCIL ACTION

None.

 

BACKGROUND

The City received three (3) bids through Cit-E-Bid for awarding a service contract for water line installation by pipe bursting and/or horizontal directional drilling (HDPE) for the Utilities Department. Estimated time for completion of this project is two hundred twenty (220) working days.  This contract shall be the responsibility of and administered between the vendor and the Utilities Department.

VIVA LAREDO PLAN ALIGNMENT
Alignment Rating: Moderate
Supporting goal(s)/policy(ies):
Policy 6.5.7 Continue to implement the existing water conservation program
Policy 7.2.4 Increase access to safe water

Summary of alignment:
This agenda item update aligns with Viva Laredo’s Comprehensive Plan goals and policies related to efficient water utilization and sustainable development.

Pricing Summary:

 

Vendor

Project Total

Murphy Pipeline Contractors

$11,153,320.00

Renoworks, LLC

$11,279,355.00

Sal Construction

$14,189,115.00

 

 

COMMITTEE RECOMMENDATION

None.

 

STAFF RECOMMENDATION

recommendation

Approve this motion.

end

Fiscal Impact

 

Fiscal Year:                                                                                                          2026.

Budgeted Y/N?:                                                                                    Yes.

Source of Funds:                                                                                     2024 Water Revenue Bond.

Account #:                                                                                                          557-9884-535-9301.

Change Order: Exceeds 25% Y/N:                      No.

 

FINANCIAL IMPACT:

Funding is available in the Waterworks Fund- 2024 Water Revenue Bond Account #557-9884-535-9301, Project ID: WP2502