Title: Authorizing City Manager to approve amendment No.1 to the Professional Engineering Services contract with Ardurra Group, Inc., Laredo, Texas. in the amount of $19,940.00 for the Tx-DOT IH 35 Utility Relocation. The total contract amount with amendment No.1 is $61,820.00. Funding is available in the Sewer System Fund- 2017 Sewer Revenue Bond
Attachments: 1. Amendment No. 1 - I-35 FM Relocation (1).pdf, 2. MHB - Flying J FM Relocation (1).pdf, 3. Aerial-Location.pdf, 4. Plan Layout.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT

title

Authorizing City Manager to approve amendment No.1 to the Professional Engineering Services contract with Ardurra Group, Inc., Laredo, Texas. in the amount of $19,940.00 for the Tx-DOT IH 35 Utility Relocation. The total contract amount with amendment No.1 is $61,820.00. Funding is available in the Sewer System Fund- 2017 Sewer Revenue Bond 

 

body

VIVA LAREDO PLAN ALIGNMENT

Alignment Rating:

None

 

 

PREVIOUS COUNCIL ACTION

N/A

 

BACKGROUND

TxDOT is currently designing IH 35 roadway improvements which requires relocating the existing utility force main under IH 35. We will be submitting a Standard Utility Agreement in order to get 100% reimbursed for the entire cost of the project.

 

COMMITTEE RECOMMENDATION

N/A

 

STAFF RECOMMENDATION

recommendation

Approval of Motion

end

Fiscal Impact

 

Fiscal Year:                                                                                                          2025

Budgeted Y/N?:                                                                                    Y

Source of Funds:                                                                                     2017 Sewer Revenue Bond

Account #:                                                                                                          559-4298-535-9301

Change Order: Exceeds 25% Y/N:                      N

 

FINANCIAL IMPACT:

Funding is available in the Sewer System Fund- 2017 Sewer Revenue Bond Account No. 559-4298-535-9301. Project ID:SW2515