Title: Consideration to award a construction contract to the lowest responsible, responsive bidder ALC Construction Co., Inc., Laredo, Texas in the amount not to exceed $303,500.00 for FY25-ENG-40 Shiloh McPherson NE Right Turn Lane & Widening Project for the total base bid including alternate #2 plus a $50,000.00 contingency allowance. Construction contract time is 60 working days. Funding is available in the 2025 Tax Note and the 2021 Certificate of Obligation Bond. 1. ALC Construction Co., Inc., Laredo, Texas Total Base Bid: $294,500.00 + Alternate #2 $9,000.00 = $303,500.00 2. CID Group Inc., Laredo, Texas Total Base Bid: $314,233.51 + Alternate #2 $10,713.00 = $324,946.51 3. SKG One-Stop Construction Inc., Laredo, Texas Total Base Bid: $392,394.82 + Alternate #2 $5,636.61 = $398,031.43 4. SAL Construction Management LLC, Laredo, Texas Total Base Bid: $474,840.00 + Alternate #2 $25,200.00 = $500,040.00 5. ABBA Construction, LLC, Laredo, Texas Total Base Bid: $572,100....
Attachments: 1. FY25-ENG-40 Award Recommendation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT
title
Consideration to award a construction contract to the lowest responsible, responsive bidder ALC Construction Co., Inc., Laredo, Texas in the amount not to exceed $303,500.00 for FY25-ENG-40 Shiloh McPherson NE Right Turn Lane & Widening Project for the total base bid including alternate #2 plus a $50,000.00 contingency allowance. Construction contract time is 60 working days. Funding is available in the 2025 Tax Note and the 2021 Certificate of Obligation Bond.

1. ALC Construction Co., Inc., Laredo, Texas
Total Base Bid: $294,500.00 + Alternate #2 $9,000.00 = $303,500.00
2. CID Group Inc., Laredo, Texas
Total Base Bid: $314,233.51 + Alternate #2 $10,713.00 = $324,946.51
3. SKG One-Stop Construction Inc., Laredo, Texas
Total Base Bid: $392,394.82 + Alternate #2 $5,636.61 = $398,031.43
4. SAL Construction Management LLC, Laredo, Texas
Total Base Bid: $474,840.00 + Alternate #2 $25,200.00 = $500,040.00
5. ABBA Construction, LLC, Laredo, Texas
Total Base Bid: $572,100.00 + Alternate #2 $9,000.00 = $581,100.00

Refer to attached letter of recommendation.

body
PREVIOUS COUNCIL ACTION
N/A

BACKGROUND
This project consists of constructing a right turn lane at the Northeast intersection of Shiloh and McPherson. The right turn lane will consist of constructing a 3,900 SF of 8" thick reinforced concrete travel lane with asphalt overlay. In addition to this, 2,050 SF of concrete sidewalk and 350 SF of concrete driveway will be added. Finally, utility relocation of water valves, utility poles, traffic poles, and storm drain inlet will be adjusted.

A total of five (5) electronic bids were received at City Secretary's office on Wednesday, March 11, 2026 at 4:00 P.M. which were publicly opened, read and taken advertisement on Thursday, March 12, 2026 at 10:00 A.M.

Contractor
Total Base Bid Including Contingency Allowance
Alternate #2
Total Base Bid + Alternate #2
ABBA Construction, LLC
$572,100.00
$9,000.00
$581,100.00
ALC Construction Co...