SUBJECT
title
Consideration for approval of amendment No. 3 an increase of $1,712,740 to the professional services contract with RS&H, Inc., San Antonio, Texas, for the Laredo International Airport Terminal Improvements Program. This amendment is for the re-packaging of design scope into four bid packages and associated Construction Administration Services. Current professional services contract with this amendment is $8,119,220.00. Funding is available through the Laredo International Airport Operation Fund.
body
PREVIOUS COUNCIL ACTION
August 2, 2021- Amendment #1
June 24, 2024- Amendment #2
VIVA LAREDO PLAN ALIGNMENT
Alignment Rating: Strong
Supporting goal(s)/policy(ies):
Goal 4.16: The Laredo International Airport will increase its role as a welcoming gateway for passengers, as an intermodal hub for incoming and outgoing goods, and as a center for related economic activities that serve the city and the region.
Summary of alignment:
The proposed amendment demonstrates strong alignment with the Viva Laredo Comprehensive Plan by advancing the implementation of the Laredo International Airport Terminal Improvements Program. The re-packaging of the design scope into four bid packages and the addition of associated Construction Administration Services will facilitate the efficient delivery and construction of planned terminal improvements.
The project directly supports Goal 4.16 by investing in the continued improvement and modernization of Laredo International Airport as a welcoming passenger gateway and regional transportation and economic asset.
BACKGROUND
The Laredo International Airport (Airport) has requested that RS&H (Consultant) provide a scope and fee for re-packaging of design scope into four bid packages and associated Construction Administration Services.
Anticipated bid packages:
Package 1 – SSCP, TSA Suite and Restrooms
- Renovation of First Floor Public Restrooms
- Renovation of First Floor FIS Restrooms
- Expanded SSCP Lane ...