SUBJECT
title
Authorizing the City Manager to approve Change Order No. 4 for the Eastern Chacon Creek Interceptor & Drainage Improvements for AZAR Services, LLC. This change order is required to complete the project deducting and adding work and materials originally specified for the project. This change order in the amount of $30,595.74 will increase the contract amount to $4,129,625.19 and add 330 working days to the original contract for a total of 842 working days. Funding is available in the 2016 Environmental Certificate of Obligation Bond.
body
PREVIOUS COUNCIL ACTION
On January 17, 2023 City Council approved Change Order No. 3.
BACKGROUND
This Change Order consists of material changes originally specified and addition of materials and work not in the original contract.
Contract Amount Working Days
Original Contract $4,361,657.20 330
Change Order No. 1 ($345,270.00) 0
Change Order No. 2 $0.00 130
Change Order No. 3 $82,642.25 65
Change Order No. 3 $30,595.74 330
Total $4,129,625.19 842
COMMITTEE RECOMMENDATION
NA
STAFF RECOMMENDATION
recommendation
Passage of the Motion.
end

Fiscal Impact
Fiscal Year: 2024
Budgeted Y/N?: Y
Source of Funds: 2016 Environmental Certificate of Obligation
Account #: 249-9871-545-9301
Change Order: Exceeds 25% Y/N: No
FINANCIAL IMPACT:
Funding is available in the 2016 Environmental Certificate of Obligation account# 249-9871-545-9301 project: 16EN04.