Consideration for approval of Change Order No. 1, an increase in the amount of $ 46,525.00 and an increase of 60 calendar days to the professional services contract with Sepulveda Associates and Architects for the North Side Materials Storage Canopy project.
Current contract with this change order is $ 319,995.00. Funding is available in the Waterworks Fund - 2020 Revenue Bond.
body
PREVIOUS COUNCIL ACTION
Click or tap here to enter text.
BACKGROUND
Authorizing the Interim City Manager to award an architectural and engineering professional
services contract to Sepulveda Associates Architects, Inc. in the amount of 237,470.00 for the
proposed North Side Materials Storage Canopy and associated site improvements. Services include schematic design phase, construction document phase, bidding and negotiation and construction administration phase. Funding is available in the 2020A Water Revenue Bond.
VIVA LAREDO PLAN ALIGNMENT
Alignment Rating: N/A
Supporting goal(s)/policy(ies): N/A
Summary of alignment: N/A
COMMITTEE RECOMMENDATION
None
STAFF RECOMMENDATION
recommendation
Approve this motion.
end

Fiscal Impact
Fiscal Year: 2026
Budgeted Y/N?: YES
Source of Funds: 2020A Water Revenue Bond
Account #: 557-9877-535-9301
Change Order: Exceeds 25% Y/N: No
FINANCIAL IMPACT:
Funding is available in the Waterworks- 2020 Revenue Bond.