SUBJECT
title
Consideration to ratify the approval of an emergency purchase order in the amount of $529,307.36 to Sunbelt Rentals for the installation of a bypass pump system in the 54” Southside sewer collector, effective from December 21, 2024, for up to four months if required, as approved by the City Manager. Funding is available in the Sewer System Fund- 2020A Sewer Revenue Bond.
body
PREVIOUS COUNCIL ACTION
None
BACKGROUND
A manhole of the 54” sanitary sewer collector collapsed on December 18, 2024. City-owned diesel pumps were on-site, preventing a major spill. The collapse occurred because the ground support for the manhole, composed of river silt, failed. The manhole, installed in 2001, eventually shifted, causing a crack in the wall. As water entered, the surrounding ground was washed out, leading to the failure. An engineering firm is being contracted to redesign the manhole foundation and assess the rest of the manholes along the line. Larger pumps are required to handle the high peak flows on this line.
COMMITTEE RECOMMENDATION
None
STAFF RECOMMENDATION
recommendation
It is recommended that this action is approved
end

Fiscal Impact
Fiscal Year: 2025
Budgeted Y/N?: Y
Source of Funds: 2020A Sewer Revenue Bond
Account #: 559-9877-535-9301
Change Order: Exceeds 25% Y/N: N
FINANCIAL IMPACT:
Funding is available on the 2020A Sewer Revenue Bond
Account Number 559-9877-535-9301
Project SW1801