SUBJECT
title
Authorizing the City Manager to accept the project as complete and request authorization to release the retainage in the amount of $425,854.22 to Honeywell International, Inc. for the Energy Savings Performance Contract (ESPC). The final contract is $8,517,084.00 and the total contract period is 965 calendar days. Funding is available in the Waterworks Fund.
body
PREVIOUS COUNCIL ACTION
On December 2, 2019 City Council Approved the construction contract to Honeywell International, Inc. in the amount of $10,009,255.00 with a contract time of 600 days for the Energy Savings Performance Contract. On May 3, 2021 Change Order #1 & #2 was approved by City Council. On October 18, 2021 Change Order #3 was approved by City Council.
BACKGROUND
Contract |
Amount |
Contract Time (Calendar Days) |
Original contract |
$10,009,255.00 |
600 |
Change Order No. 1 & No. 2 |
$10,009,255.00 |
365 |
Change Order No. 3 |
($1,247,000.00) |
0 |
Current Contract |
$8,517,084.00 |
965 |
COMMITTEE RECOMMENDATION
N/A
STAFF RECOMMENDATION
recommendation
Approve Motion
end

Fiscal Impact
Fiscal Year: 2025
Budgeted Y/N?: Y
Source of Funds: Retainage
Account #: 557-0000-206-0100
Change Order: Exceeds 25% Y/N: N
FINANCIAL IMPACT:
Funding is available in the Retainage Account