Title: Authorizing the City Manager to approval of change order No. 1 in the amount of $18,297.14 and increase of 15 working days to the contract time. This change order is required to complete the project, adding material not included in the original contract. With this change order the contract amount with J.S. Haren Company will increase the contract to a total of $5,233,497.14 and 305 days working days. Funding is available in the Waterworks Fund- 2020A Water Revenue Bond.
Attachments: 1. 25-1777 Eng 10.6.25
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT

title

Authorizing the City Manager to approval of change order No. 1 in the amount of $18,297.14 and increase of 15 working days to the contract time. This change order is required to complete the project, adding material not included in the original contract. With this change order the contract amount with J.S. Haren Company will increase the contract to a total of $5,233,497.14 and 305 days working days. Funding is available in the Waterworks Fund- 2020A Water Revenue Bond.

 

body

VIVA LAREDO PLAN ALIGNMENT

Alignment Rating: Moderate

Supporting goal(s)/policy(ies): Policy 6.5.7 Continue to implement the existing water conservation program

Policy 7.2.4 Increase access to safe water

 

Summary of alignment: This agenda item update aligns with Viva Laredo’s Comprehensive Plan goals and policies addressing water quality by replacing aged water lines.

 

PREVIOUS COUNCIL ACTION

On October 28, 2024, the City Council approved the construction contract to the sole responsive bidder J.S. Haren Company from Athens, Tennessee in the amount of $5,215,200.00 for the Chlorine Dioxide Improvements for El Pico Surface and Jefferson Water Treatment Plants.

 

BACKGROUND

It is recommended to proceed with the Combination Degassing Valve option. This option includes both a degassing valve and an air release valve, offering improved functionality.

Contract
                                         Amount                                      Days
Original Contract
                           $5,215,200.00                           290
Change Order No. 1      $18,297.14
                           15
Total
                                                $5,233,497.14                           305

 

COMMITTEE RECOMMENDATION

None

 

STAFF RECOMMENDATION

recommendation

Approval of Motion

end

Fiscal Impact

 

Fiscal Year:                                                                                                          2025

Budgeted Y/N?:                                                                                    Y

Source of Funds:                                                                                     2020A Water

Account #:                                                                                                          557-9877-535-9301

Change Order: Exceeds 25% Y/N:                      N

 

FINANCIAL IMPACT:

Funding is available in the Waterworks Fund- 2020A Water Revenue Fund Acct. No.557-9877-535- 9301, $2,412,386.25 Project ID: WP2501