Skip to main content

File #: 26-722    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 4/2/2026 In control: City Council
On agenda: 4/20/2026 Final action:
Title: Authorizing the City Manager for the award of RFQ 2026-047 Engineering, Planning, Design, Procurement, Construction and Project Management contract for a new Drinking Water and Wastewater Laboratory to Sepulveda Associates Architects, Inc. This will be a capital expense and is related to improving and extending the City of Laredo combined Waterworks System and Sewer System. The term of this contract shall be for a period of twenty four months. The location of the laboratory will be evaluated by the awardee and will be built on city owned property as required. Funding is available in the Waterworks and Sewer System Funds - 2024 Water and Sewer Revenue Bonds.
Attachments: 1. WQ Attch Water - WW Lab Sheila File ID 26-722 CCM 4-20-26, 2. EFQ 2026-047 Evaluation Matrix Final Updated
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT
title
Authorizing the City Manager for the award of RFQ 2026-047 Engineering, Planning, Design, Procurement, Construction and Project Management contract for a new Drinking Water and Wastewater Laboratory to Sepulveda Associates Architects, Inc. This will be a capital expense and is related to improving and extending the City of Laredo combined Waterworks System and Sewer System. The term of this contract shall be for a period of twenty four months. The location of the laboratory will be evaluated by the awardee and will be built on city owned property as required. Funding is available in the Waterworks and Sewer System Funds - 2024 Water and Sewer Revenue Bonds.

body

PREVIOUS COUNCIL ACTION
BACKGROUND
During the September 15, 2025, City Council meeting, it was determined that third-party contracting for certain water and wastewater sampling is currently necessary, as the Utilities Department does not have the capability to perform all required sampling and analysis in-house.

To address this limitation and enhance operational efficiency, the Utilities Department is in the process of developing its own water and wastewater laboratory. Once completed, this facility will allow the department to conduct sample analysis internally, improving turnaround times and reducing reliance on external contractors.

VIVA LAREDO PLAN ALIGNMENT
Alignment Rating: N/A
Supporting goal(s)/policy(ies): N/A
Summary of alignment: N/A

COMMITTEE RECOMMENDATION
N/A

STAFF RECOMMENDATION
recommendation
It is recommended that this bid be awarded.
end

Fiscal Impact

Fiscal Year: FY25-26
Budgeted Y/N?: Yes
Source of Funds: 2024 Water Revenue Bond
Account #: 557-9884-535-9301 Project ID WP2603 (50%)
559-9884-535-9301 Project ID SW2602 (50%)
Change Order: Exceeds 25% Y/N: N/A

FINANCIAL IMPACT:
2024 Water and Sewer Revenue Bonds will be used for this capital improvement project...