SUBJECT
title
Consideration to award a professional services contract to Sepulveda Associates Architects, Inc., in the amount of $424,220.50 for the FY26-ENG-47 5508 Thomas Ave. Police Department Offices and Evidence Room Building Enhancements Project for architectural and engineering services. Funding is available in the 2023 Certificate of Obligation Bond.
body
PREVIOUS COUNCIL ACTION
N/A
BACKGROUND
Proposal includes architectural and engineering services for the complete design and documentation of the full office/storage evidence warehouse and site improvements build-out scope required to satisfy the applicable local Police Department and State requirements.
Total A/E Compensation Pay and Task Schedule is proposed:
Task One Schematic & Design Development Phase $125,790.00 3-5 Weeks
Task Two: Construction Document Phase $134,225.00 6-8 Weeks
Task Three: Bidding and Negotiation $ 16,890.00 4-5 Weeks
Task Four: Construction Administration Phase 1 $108,750.00 150-180 Working Days
Total $385,655.00 BASE PROPOSAL
Contingency Allowance - 10% (Rec. for Remodeling) $ 38,565.50 OPTIONAL
TOTAL AMOUNT with Contingency Allowance $424,220.50
COMMITTEE RECOMMENDATION
N/A
STAFF RECOMMENDATION
recommendation
Approval of this motion.
end

Fiscal Impact
Fiscal Year: 2026
Budgeted Y/N?: Y
Source of Funds: 2023 CO Bond
Account #: 476-2310-525-9301
Change Order: Exceeds 25% Y/N: N/A
FINANCIAL IMPACT:
Funding is available in the 2023 Certificate of Obligation Bond.
Account # 476-2310-525-9301 pd2603