File #: 24-1117    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 5/24/2024 In control: City Council
On agenda: 6/24/2024 Final action:
Title: Consideration to award a construction contract to the lowest responsible, responsive bidder Mage 4Group, Ltd. Laredo, Texas, in an amount not to exceed $1,860,521.00 for the FY24-ENG-48 Springfield Avenue Phase 2A project for the total base bid including a $200,000.00 contingency allowance. The construction contract time for the project is 135 working days. Funding is available in the Capital Grants Fund. 1. Mage 4Group, Ltd. Laredo, Texas Total Base Bid Amount $1,860,521.00 2. Texas Guardrail Contractors LLC, DBA - STX Civil, Laredo, Texas Total Base Bid Amount $2,219,080.38 Attached is a letter of recommendation from Gilpin Engineering Company, Laredo, Texas.
Attachments: 1. FY24-ENG-48 - Letter of Recommendation - Bid Tabulation, 2. FY24-ENG-48 - City Secretary, 3. FY24-ENG-48 - Supplier Response (G4 Construction Co.), 4. FY24-ENG-48 - Supplier Response (STX Civil)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT
title
Consideration to award a construction contract to the lowest responsible, responsive bidder Mage 4Group, Ltd. Laredo, Texas, in an amount not to exceed $1,860,521.00 for the FY24-ENG-48 Springfield Avenue Phase 2A project for the total base bid including a $200,000.00 contingency allowance. The construction contract time for the project is 135 working days. Funding is available in the Capital Grants Fund.

1. Mage 4Group, Ltd. Laredo, Texas
Total Base Bid Amount $1,860,521.00
2. Texas Guardrail Contractors LLC, DBA - STX Civil, Laredo, Texas
Total Base Bid Amount $2,219,080.38

Attached is a letter of recommendation from Gilpin Engineering Company, Laredo, Texas.

body
PREVIOUS COUNCIL ACTION
On March 29, 2021, City Council approved Ordinance No. 2022-O-120 authorizing the Interim City Manager to accept an Economic Development Administration Grant in the amount of $1,500,000.00, with a local match of $375,000.00 for a total of $1,875,000.00 for the Springfield Road Extension Phase II. Also, authorizing the Interim City Manager to amend the FY22 Capital Grant Budget by appropriating revenues and expenses in the same amount. Local match will be from the 2019 Certificate of Obligation bond.

BACKGROUND
The project consists of constructing a five (5) lane concrete pavement roadway that includes the following: Constructing a 9" concrete pavement roadway (820 LF), 12" diameter water line DR-14 PVC, 8" diameter sanitary sewer line SDR-26, traffic signal, street lights, 12' sidewalks, utility conduit crossings, etc.

Construction contract time for the project is One Hundred Thirty-Five (135) working days.

Two (2) electronic bids, were received at City Secretary's Office, 1110 Houston Street, 3rd floor, City Hall Building, Laredo, Texas, on Thursday, May 30, 2024 and publicly opened, read, and taken under advisement on Friday, May 31, 2024 at 11:30 A.M.

Contractor
Total Base Bid (including Contingency Allowance)
Mage 4Group, Ltd, Laredo, Texas
$...

Click here for full text