SUBJECT
title
Preliminary consideration of the plat of Los Cielos at Cielito Lindo Subdivision, Phase I. The intent is residential.
PL-039-2026
District I - Cm. Gilbert Gonzalez
body
PREVIOUS COUNCIL ACTION
N/A
BACKGROUND
APPLICANT: TDB Land Holdings, LTD
ENGINEER: Top Site Civil Group, LLC
SITE: This 23.64-acre tract of land is located east of St. Luke and Solomon Casseb Rd. The zoning for this 165-lot development is R-1B (Single-Family High-Density District). This tract is located in District I - Cm. Gilbert Gonzalez.
COMMITTEE RECOMMENDATION
N/A
STAFF RECOMMENDATION
recommendation
APPROVE SUBJECT TO THE FOLLOWING COMMENTS:
Planning:
1. The proposed subdivision does not comply with the Future Thoroughfare Plan in that St. Luke Boulevard is to extend as a collector in a southerly direction followed by a westerly connection towards Ejido Avenue. Revise accordingly.
2. Phase I includes streets that exceed the maximum allowed continuous street length of 1,000 feet for local residential streets. Revise the street layout to comply with Section 3-2 N. 2. a. of the Subdivision Ordinance.
3. Phase I includes blocks that exceed the maximum allowable block length of 1,200 feet. Revise the layout accordingly to comply with Section 3-2 N. 1. of the Subdivision Ordinance.
4. The westernmost entrance of Phase I (Street F) creates a street jog with the westernmost entrance of Phase II (Street A). Revise the layout accordingly.
5. Provide street names.
6. Provide lot dimensions for all lots.
7. Provide a Lot Summary Table.
8. Provide a scale on the vicinity map and ensure the scale is 1” = 2000’.
9. Add a plat note prohibiting direct access to St. Luke Boulevard from Lot 1, Block 10.
10. Ensure all text (bearings and distances) is legible on the drawing, particularly at the intersection of Street H and Street L, where text appears to overlap.
11. Revise the title block to reflect Porcion 39, Abstract 250, and not Survey 39.
12. Identify the purpose of the line running in a north-south direction traversing Block 16.
13. Label Lot 13, Block 8 to reference Plat Note 12, identifying it as a drainage easement and unbuildable.
14. Coordinate with the Traffic Department for the driveway placement for Lot 1, Block 10, due to its close proximity to St. Luke Boulevard. An increase in lot width may be necessary.
15. The subdivision identifies TDB World Industrial Park, LLC as the owner within the title block. Update the owner/developer as TDB Land Holdings, Ltd as per the application and deed.
16. Access to Cuatro Vientos is subject to the review and approval by the Texas Department of Transportation (TX-DOT).
17. Identify all easements.
18. All improvements as per the Subdivision Ordinance.
Fire:
1. Fire hydrants required every 500 feet for residential development.
2. Temporary turnaround required for dead end roads over 150 feet (96-foot cul de sac, 120-foot hammerhead, 60-foot Y).
Traffic: No comments submitted.
Parks & Leisure: No comments submitted.
Engineering: No comments submitted.
Environmental: No comments submitted.
Water & Utilities: No comments submitted.
WEBB County App: No comments submitted.
AEP Engineers: No comments submitted.
U.I.S.D.: No comments submitted.
L.I.S.D.: No comments submitted.
AT&T: No comments submitted.
NOTICE TO THE DEVELOPER:
Planning:
1. Only the utility easements within the plat boundaries are subject to change prior to plat recordation due to revisions by the utility companies.
2. All comments set forth are preliminary comments and not an exhaustive list. Additional comments may be added prior to final plat approval.
end