File #:
|
25-1336
Version:
1
|
|
|
Type:
|
Consent Agenda
|
Status:
|
Agenda Ready
|
On agenda:
|
8/4/2025
|
Final action:
|
|
Title:
|
Consideration to award a construction contract to the lowest, responsible, responsive bidder American Contracting & Roofing, Laredo, Texas in the amount not to exceed $409,000.00 for FY24-ENG-52-A Plaza Theatre Roof Replacement Project for the total base bid including a $75,000.00 contingency allowance. Construction contract time is 100 working days. Funding is available in the Housing Rehabilitation Fund - HUD EDI Grant.
1. American Contracting and Roofing, Laredo, Texas
Total Base Bid: $409,000.00
2. Quantum Construction (Quantcorp Construction), Laredo, Texas
Total Base Bid: $438,800.00
3. JJ Flores Roofing (Roofing and Construction by JJ Flores), Laredo, Texas
Total Base Bid: $452,900.00
4. ARGIO Roofing & Construction LLC, Harlingen, Texas
Total Base Bid: $629,610.6
5. ABBA CONSTRUCTION, LLC, Laredo, Texas
Total Base Bid: $650,019.00
Refer to attached letter of recommendation from Able City, Laredo, Texas.
|

SUBJECT
title
Consideration to award a construction contract to the lowest, responsible, responsive bidder American Contracting & Roofing, Laredo, Texas in the amount not to exceed $409,000.00 for FY24-ENG-52-A Plaza Theatre Roof Replacement Project for the total base bid including a $75,000.00 contingency allowance. Construction contract time is 100 working days. Funding is available in the Housing Rehabilitation Fund - HUD EDI Grant.
1. American Contracting and Roofing, Laredo, Texas Total Base Bid: $409,000.00 2. Quantum Construction (Quantcorp Construction), Laredo, Texas Total Base Bid: $438,800.00 3. JJ Flores Roofing (Roofing and Construction by JJ Flores), Laredo, Texas Total Base Bid: $452,900.00 4. ARGIO Roofing & Construction LLC, Harlingen, Texas Total Base Bid: $629,610.6 5. ABBA CONSTRUCTION, LLC, Laredo, Texas Total Base Bid: $650,019.00
Refer to attached letter of recommendation from Able City, Laredo, Texas.
body
VIVA LAREDO PLAN ALIGNMENT
Alignment Rating: Strong
Supporting goal(s)/policy(ies):
Policy 9.2.3 Preserve and rehabilitate historic buildings, particularly those in Downtown and designated historic districts.
Policy 9.2.6 Encourage reinvestment in Downtown Laredo through infrastructure improvements and building upgrades.
Policy 6.22.4 Design and build city facilities that are resource-efficient, sustainable, and promote long-term cost savings.
Summary of alignment:
The Plaza Theatre Roof Replacement Project shows strong alignment with the Viva Laredo Comprehensive Plan by advancing the preservation and rehabilitation of a culturally significant downtown building. The project reinforces key planning goals focused on historic preservation, downtown revitalization, and public infrastructure renewal.
PREVIOUS COUNCIL ACTION
N/A
BACKGROUND
The City of Laredo Plaza Theatre is an existing movie theatre building located in downtown Laredo, TX. The work includes the removal of the roof's existing MEP, HVAC equipment, equipment curbs, ducts, vents, piping, conduit, electric boxes, roof insulation and top roofing membrane. Refer to demolition plans for more information on scope. The existing roof deck will remain and be repaired based on the contractor's assessment after uncovering. The contractor will then provide and install new insulation, roof membrane and accessories, metal coping and trim as per the construction documents. Construction contract time for the project is one hundred days (100) working days.
A total of seven (7) electronic bids were received at the City Secretary’s office on Wednesday, July 9, 2025 at 4:00 P.M. which were publicly opened, read and taken advertisement on Thursday, July 10, 2025 at 10:00 A.M. Of the seven (7) bids, only five (5) bidders included all of the required documentation (including Bid Bonds).
Contractor |
Total Base Bid Including Contingency Allowance |
Submission of All Required Documentation |
JABK Homes LLC, Laredo, Texas |
$245,000.00 |
No |
AAA Roofing LLC, Brackettville, Texas |
$346,550.00 |
No |
American Contracting and Roofing, Laredo, Texas |
$409,000.00 |
Yes |
Quantum Construction (Quantcorp Construction), Laredo, Texas |
$438,800.00 |
Yes |
JJ Flores Roofing (Roofing and Construction by JJ Flores), Laredo, Texas |
$452,900.00 |
Yes |
ARGIO Roofing & Construction LLC, Harlingen, Texas |
$629,610.6 |
Yes |
ABBA CONSTRUCTION, LLC, Laredo, Texas |
$650,019.00 |
Yes |
Refer to attached letter of recommendation from Able City, Laredo, Texas.
COMMITTEE RECOMMENDATION
N/A
STAFF RECOMMENDATION
recommendation
Approval of this motion.
end

Fiscal Impact
Fiscal Year: 2025
Budgeted Y/N?: Y
Source of Funds: Housing Rehabilitation Fund
Account #: 212-5023-545-9201
Change Order: Exceeds 25% Y/N: N/A
FINANCIAL IMPACT:
Funding is available in the Housing Rehabilitation Fund- HUD EDI Grant. Account# 212-5023-545-9201 Project# 23EDPT
|