File #: 24-0351    Version: 1
Type: Consent Agenda Status: Passed
File created: 2/1/2024 In control: City Council
On agenda: 2/20/2024 Final action: 2/20/2024
Title: Consideration for approval of FY23-ENG-04 Market St. Elderly Affordable Rental Housing Project located at 810 Sanders Avenue project as complete, approval of change order No.1, a total decrease in the amount of $48,450.00, and an increase in contract time of 32 calendar days to adjust for final project close-out items, release of retainage, and approval of final payment in the amount of $58,677.50 to Midas Contractors, LLC. The final construction contract amount, including this change order, is $1,173,550.00 with a construction contract time of two hundred and twelve (212) calendar days. Funding is available in the Home Investment Partnership Program Fund.
Attachments: 1. FY23-ENG-04 Change Order 1

SUBJECT

title

Consideration for approval of FY23-ENG-04 Market St. Elderly Affordable Rental Housing Project located at 810 Sanders Avenue project as complete, approval of change order No.1, a total decrease in the amount of $48,450.00, and an increase in contract time of 32 calendar days to adjust for final project close-out items, release of retainage, and approval of final payment in the amount of $58,677.50 to Midas Contractors, LLC. The final construction contract amount, including this change order, is $1,173,550.00 with a construction contract time of two hundred and twelve (212) calendar days. Funding is available in the Home Investment Partnership Program Fund.

 

body

PREVIOUS COUNCIL ACTION

On January 17, 2023, City Council awarded a construction contract FY23-ENG-04 to the lowest responsible responsive bidder Midas Contractors, LLC., Laredo, Texas; in the amount not to exceed $1,222,000.00 for Market St. Elderly Affordable Rental Housing Project located at 810 Sanders Avenue, Laredo, Texas including total base bid, and total deductive alternates 1 through 4, consisting of constructing of a seven single unit affordable housing project complex with associated site and utility improvements. The construction contract time for the project is 180 calendar days and authorizing the Interim City Manager to execute all related contract documents contingent upon receipt and approval of insurance and bond documents. Funding is available in the Home Investment Partnerships Program.


Two (2) electronic bids through Cit-E-Bid and one (1) manual bid were received at the City Secretary’s office on or before Thursday, December 8, 2022, at 4:00 P.M. The bids received were publicly opened, read and taken under advertisement on Friday, December 9, 2022, at 10:00 A.M.


The three (3) bids and bid bonds received were reviewed by Sepulveda Associates Architects, Inc., and attached is the letter of recommendation.

 

Company Name

Summary Totals (Base Bid including Deductive Alternates 1 through 4)

Hud Section 3 Vendor

Zertuche Construction Texas LLC, Laredo, Texas

$1,239,233.00

No

ALC Contractors, Laredo, Texas

$1,247,273.87

Yes

Midas Contractors LLC., Laredo, Texas

$1,222,000.00

Yes

 

BACKGROUND

The City of Laredo will solicit and receive bids for FY23-ENG-04 Market Street Elderly Affordable Rental Housing Project located at 810 Sanders Avenue, Laredo, Texas 78040 consists of a seven single unit affordable housing project complex with associated site and utility improvements per the prepared plans and specifications dated September 16, 2022, from Project Architect - Sepulveda Associates Architects, Inc.
Two (2) electronic bids through Cit-E-Bid and one (1) manual bid were received at the City Secretary’s office on or before Thursday, December 8, 2022, at 4:00 P.M. The bids received were publicly opened, read and taken under advertisement on Friday, December 9, 2022, at 10:00 A.M.


The three (3) bids and bid bonds received were reviewed by Sepulveda Associates Architects, Inc. as follows:

 

Contractor

Base Bid (Includes all  Allowances)

Total Deductive  Alternates 1-4

Summary Totals (Base Bid including Deductive Alternates  1 through 4)

Hud Section 3 Vendor

Zertuche Construction Texas LLC, Laredo, Texas

$1,344,550.00

($105,317.00)

$1,239,233.00

No

ALC Contractors, Laredo, Texas

$1,368,273.87

($121,000.00)

$1,247,273.87

Yes

Midas Contractors LLC., Laredo, Texas

$1,385,000.00

($163,000.00)

$1,222,000.00

Yes


The final construction contract amount, including this change order, is $1,173,550.00 with a construction contract time of two hundred and twelve (212) calendar days.

 

Original Contract Amount                                                                $1,222,000.00                      

Decrease in Contract Amount                                            $48,450.00                      

Revised Contract Amount                                                                $1,173,550.00                      

                                                                                    

Original Contract Time:                                                               180 Calendar Days                     

Increase in Contract Time:                                                               32 Calendar Days                      

Revised Contract Time:                                                                212 Calendar Days                      

 

COMMITTEE RECOMMENDATION

N/A

 

STAFF RECOMMENDATION

recommendation

Approval of this motion.

end

Fiscal Impact

 

FINANCIAL IMPACT:

Fiscal Year:                                                                                                         2024

Budgeted Y/N?:                                                                                    Y

Source of Funds:                                                                                    2019 Home Investment Part. Grant

Account #:                                                                                                         217-6963-563-7540

Change Order: Exceeds 25% Y/N:                      No                     

 

Fiscal Year:                                                                                                         2024

Budgeted Y/N?:                                                                                    Y

Source of Funds:                                                                                    2021 Home Investment Part. Grant

Account #:                                                                                                         217-6965-563-7542

Change Order: Exceeds 25% Y/N:                     No

 

Fiscal Year:                                                                                                         2024

Budgeted Y/N?:                                                                                    Y

Source of Funds:                                                                                    2022 Home Investment Part. Grant

Account #:                                                                                                         217-6967-563-7542

Change Order: Exceeds 25% Y/N:                     

 

FINANCIAL IMPACT:

Funding is available in the Home Investment Partnership Program under 2019, 2021, and 2022 Home Investment Grants.