Title: Consideration to award a construction contract to the lowest responsible, responsive bidder Midas Contractors, LLC, Laredo, Texas, in the amount not to exceed $232,300.00 for the FY26-ENG-34 Housing Rehabilitation - 419B Zaragoza Street Project for the total base bid and alternate no. 1. The construction contract time is 90 calendar days. Funding is available in the Community Development Block Grant (CDBG) 50th Action Year - 2024. 1. Midas Contractors, LLC, Laredo, Texas Total Base Bid: $219,800.00 + Alternate No. 1: $12,500.00 = $232,200.00 2. Zertuche Construction Texas, LLC, Laredo, Texas Total Base Bid: $261,333.00 + Alternate No. 1: $11,333.00 = $272,666.00 Refer to attached letter from Sepulveda Associates Architects, Inc., Laredo, Texas
Attachments: 1. Award Letter of Recomendation 6-26-26
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT

title

Consideration to award a construction contract to the lowest responsible, responsive bidder Midas Contractors, LLC, Laredo, Texas, in the amount not to exceed $232,300.00 for the FY26-ENG-34 Housing Rehabilitation - 419B Zaragoza Street Project for the total base bid and alternate no. 1. The construction contract time is 90 calendar days. Funding is available in the Community Development Block Grant (CDBG) 50th Action Year - 2024.

1. Midas Contractors, LLC, Laredo, Texas
    Total Base Bid: $219,800.00 + Alternate No. 1: $12,500.00 = $232,200.00
2. Zertuche Construction Texas, LLC, Laredo, Texas
    Total Base Bid: $261,333.00 + Alternate No. 1: $11,333.00 = $272,666.00

Refer to attached letter from Sepulveda Associates Architects, Inc., Laredo, Texas

body

 

PREVIOUS COUNCIL ACTION

N/A

 

BACKGROUND

The project consists of a seven single unit affordable housing project complex with associated site and utility improvements per the prepared plans and specifications dated March 20, 2026, from Project Architect - Sepulveda Associates Architects, Inc.
Construction contract time is 90 calendar days.

A total of two (2) electronic bids were received at City Secretary’s office on Thursday, June 25, 2026 at 4:00 P.M. which were publicly opened, read and taken advertisement on Friday, June 26, 2026, at 10:00 A.M.

 

 

Total Base Bid

Alternate No. 1

Total Base Bid including Alternate No. 1

Midas Contractors, LLC

$219,800.00

$12,500.00

$232,200.00

Zertuche Construction Texas, LLC

$261,333.00

$11,333.00

$272,666.00

 

Refer to attached letter from Sepulveda Associates Architects, Inc., Laredo, Texas

 

COMMITTEE RECOMMENDATION

N/A

 

STAFF RECOMMENDATION

recommendation

Approval of this motion.

end

Fiscal Impact

 

Fiscal Year:                                                                                                          2026

Budgeted Y/N?:                                                                                    Y

Source of Funds:                                                                                     CDBG - 50th Action Year 2024

Account #:                                                                                                          211-9650-535-1446

Change Order: Exceeds 25% Y/N:                      N/A

 

FINANCIAL IMPACT:

Funding is available in the Community Development Block Grant (CDBG) 50th Action Year - 2024.
Account #: 211-9650-535-1446