File #: 25-640    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 4/3/2025 In control: City Council
On agenda: 4/22/2025 Final action:
Title: Authorizing City Manager to approve amendment No. 3 for professional engineering and surveying services contract with Porras Nance Engineering of Laredo, Texas in the amount of $86,700.00 for the Relocation of Utilities on US59 / Loop 20. The total contract amount with amendment No. 3 is $1,430,310.00. Funding is available in the Waterworks Fund- 2020A Water Revenue Bond and Sewer System Fund- 2017 Sewer Revenue Bond.
Attachments: 1. Amendment 3 - LP20 Relocation.pdf, 2. FeeProposal Hrs Amendmt 3.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT

title

Authorizing City Manager to approve amendment No. 3 for professional engineering and surveying services contract with Porras Nance Engineering of Laredo, Texas in the amount of $86,700.00 for the Relocation of Utilities on US59 / Loop 20. The total contract amount with amendment No. 3 is $1,430,310.00. Funding is available in the Waterworks Fund- 2020A Water Revenue Bond and  Sewer System Fund- 2017 Sewer Revenue Bond.

 

body

PREVIOUS COUNCIL ACTION

On March 29, 2021, City Council approved a motion authorizing the City Manager to negotiate a contract for the professional engineering services for the Relocation of Utilities on US59 / Loop 20 to Porras Nance Engineering.
On May 3, 2021 City Council approved the award of professional engineering services contract in the amount of $809,250.00 to Porras Nance Engineering. On January 18, 2022 City Council approved amendment #1 in the amount of $75,000 to Porras Nance Engineering. On June 21, 2022 City Council approved amendment #2A and 2B in the amount of $459,360.00 to Porras Nance Engineering.

 

BACKGROUND

TxDOT recently adjusted the Utility Corridor offsets for this project creating a realignment of the proposed water and sewer main along the entire project. Stations and profiles must be reevaluated in detail and redesign accordingly. TxDOT needs to pay 100% the cost of Engineering Services, due to the re-design. TxDOT also extended the projects limits 6500 Lf. to the south of the Holiday Inn along US59 to the Airport Property.
This amendment #3 is required due to TxDOT requires all abandoned water and sewer mains remaining within State ROW to be filled with concrete slurry.

 

 

Amount

Original Contract

$809,250.00

Amendment No. 1

$75,000.00

Amendment No. 2A

$70,260.00

Amendment No. 2B

$389,100.00

Amendment No. 3

$86,700.00

Total Contract Amount

$1,430,310.00

 

COMMITTEE RECOMMENDATION

N/A

 

STAFF RECOMMENDATION

recommendation

Approval for Motion

end

Fiscal Impact

 

Fiscal Year:                                                                                                          2025

Budgeted Y/N?:                                                                                    Y

Source of Funds:                                                                                     2017 Sewer Revenue Bond

Account #:                                                                                                          559-4298-535-9301

Change Order: Exceeds 25% Y/N:                      N

 

FINANCIAL IMPACT:

Funding is available in the 2017 Sewer Revenue Bond account No. 559-4298-535-9301. Project ID: SW2117