File created: 10/23/2026 In control: City Council
On agenda: 11/16/2026 Final action:
Title: Consideration to reject all bids received for FY26-ENG-01 Jefferson Convenience Center – Phase 1 Project, as the bids received exceed estimated budgeted amount. There is no financial impact at this time. 1. Mage 4Group, Ltd, Laredo, Texas Total Base Bid: $1,354,740.00 2. Cid Group, Inc, Laredo, Texas Total Base Bid: $1,383,438.12 3. ALC Construction Co., Inc., Laredo, Texas Total Base Bid: $1,500,970.00 4. Alcan Contracting LLC, Laredo, Texas Total Base Bid: $1,513,578.75 5. Cobalt Construction, Laredo, Texas Total Base Bid: $1,601,132.00 6. 21 Construction Services, LLC, Laredo, Texas Total Base Bid: $1,680,802.50 7. SAL Construction Management, LLC, Weslaco, Texas Total Base Bid: $1,699,065.00 8. Gilmar Construction Ltd, Laredo, Texas Total Base Bid: $1,794,726.00 9. 360 General Contractor Inc., Laredo, Texas Total Base Bid: $1,805,085.72 10. ABBA Construction, LLC, Laredo, Texas Total Base Bid: $2,704,100.00 11. Sima Contractors, LLC, Laredo, Texas ...
Attachments: 1. FY26-ENG-01 Recommendation Letter
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT

title

Consideration to reject all bids received for FY26-ENG-01 Jefferson Convenience Center - Phase 1 Project, as the bids received exceed estimated budgeted amount. There is no financial impact at this time.

1. Mage 4Group, Ltd, Laredo, Texas
   Total Base Bid: $1,354,740.00
2. Cid Group, Inc, Laredo, Texas
   Total Base Bid: $1,383,438.12
3. ALC Construction Co., Inc., Laredo, Texas
   Total Base Bid: $1,500,970.00
4. Alcan Contracting LLC, Laredo, Texas
   Total Base Bid: $1,513,578.75
5. Cobalt Construction, Laredo, Texas
   Total Base Bid: $1,601,132.00
6. 21 Construction Services, LLC, Laredo, Texas
   Total Base Bid: $1,680,802.50
7. SAL Construction Management, LLC, Weslaco, Texas
   Total Base Bid: $1,699,065.00
8. Gilmar Construction Ltd, Laredo, Texas
   Total Base Bid: $1,794,726.00
9. 360 General Contractor Inc., Laredo, Texas
   Total Base Bid: $1,805,085.72
10. ABBA Construction, LLC, Laredo, Texas
   Total Base Bid: $2,704,100.00
11. Sima Contractors, LLC, Laredo, Texas
   Total Base Bid: $2,869,130.00
12. RAVA Construction LLC, Houston, Texas
   Total Base Bid: $3,121,000.00

Refer to attached letter of recommendation.

body

PREVIOUS COUNCIL ACTION

N/A

 

BACKGROUND

This project consists of constructing 72,500 SF of 7” heavy duty reinforced concrete, 7,150 SF of 10” reinforced concrete with imbedded steel plates, curb & gutter, a 4’ height vehicular ramp with 6’ walls, valley gutters, extension of utility lines, clearing &
grubbing, demolition, ADA ramps at driveways, fence removal & replacement, and subsidiary work.
Construction contract time for the project is ninety (90) working days.

A total of twelve (12) bids were received at City Secretary’s office on Friday, October 23, 2026 at 4:00 P.M. which were publicly opened, read and taken advertisement on Monday, October 26, 2026, at 10:00 A.M.

 

Vendor

Total Base Bid

21 Construction Services, LLC

$1,680,802.50

360 General Contractor Inc.

$1,805,085.72

ABBA Construction, LLC

$2,704,100.00

ALC Construction Co., Inc.

$1,500,970.00

Alcan Contracting LLC

$1,513,578.75

Cid Group, Inc

$1,383,438.12

Cobalt Construction

$1,601,132.00

G4 Construction Co (Mage 4Group, Ltd)

$1,354,740.00

Gilmar Construction Ltd

$1,794,726.00

RAVA Construction LLC

$3,121,000.00

SAL Construction Management, LLC

$1,699,065.00

Sima Contractors, LLC

$2,869,130.00

 

 

COMMITTEE RECOMMENDATION

N/A

 

STAFF RECOMMENDATION

recommendation

Approval of this motion.

end

Fiscal Impact

 

Fiscal Year:                                                                                                           

Budgeted Y/N?:                                                                                     

Source of Funds:                                                                                      

Account #:                                                                                                           

Change Order: Exceeds 25% Y/N:                       

 

FINANCIAL IMPACT:

There is no financial impact at this time.