File #: 25-1782    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 9/10/2025 In control: City Council
On agenda: 10/6/2025 Final action:
Title: The City Manager is hereby authorized to approve Change Order No. 1, which includes a credit in the amount of $50,000.00 for the elimination of cathodic protection and an extension of the contract time by 90 working days. This change order is necessary due to additional work not specified in the original contract with Southern Trenchless Solutions for the 36-inch Water Transmission Main from Zacate Creek to Lyon Booster Station. With approval of this change order, the total contract amount will be $9,775,340.00, and the contract duration will be extended to 270 working days. Funding for this contract is available through the Waterworks Fund- 2022 Water Revenue Bond.
Attachments: 1. 25-1782 Eng Attch 10.6.25
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT

title

The City Manager is hereby authorized to approve Change Order No. 1, which includes a credit in the amount of $50,000.00 for the elimination of cathodic protection and an extension of the contract time by 90 working days. This change order is necessary due to additional work not specified in the original contract with Southern Trenchless Solutions for the 36-inch Water Transmission Main from Zacate Creek to Lyon Booster Station. With approval of this change order, the total contract amount will be $9,775,340.00, and the contract duration will be extended to 270 working days. Funding for this contract is available through the Waterworks Fund- 2022 Water Revenue Bond.

 

body

VIVA LAREDO PLAN ALIGNMENT

Alignment Rating: Moderate

Supporting goal(s)/policy(ies): Policy 6.5.7 Continue to implement the existing water conservation program Policy 7.2.4 Increase access to safe water

Summary of alignment: This agenda item update aligns with Viva Laredo’s Comprehensive Plan goals and policies addressing water quality by replacing aged water lines.

 

PREVIOUS COUNCIL ACTION

On March 18, 2024 the City Council approved the construction contract to Southern Trenchless Solutions in the amount of $9,731,995.00 with a contract time of 180 working days for the 36-inch Water Transmission Main from Zacate Creek to Lyon Booster Station.

 

BACKGROUND

This change order is for a credit of (50,000.00)

Contract
                                             Amount                            Working Days
Original Contract
                            $9,731,995.00                                   180
Change Order No. 1     ($50,000.00)
                                   90
Additional work
                            $93,345.00                     
Total
                                                  $9,775,340.00                                  270

 

COMMITTEE RECOMMENDATION

N/A

 

STAFF RECOMMENDATION

recommendation

Approval of Motion

end

Fiscal Impact

 

Fiscal Year:                                                                                                          2025

Budgeted Y/N?:                                                                                    Yes

Source of Funds:                                                                                     2022 Water Revenue Bond

Account #:                                                                                                          557-9879-535-9301

Change Order: Exceeds 25% Y/N:                      No

 

FINANCIAL IMPACT:

Funding is available in the 2022 Water Revenue Bond. Account 557-9879-535-9301. Project ID: WP2204