Legislation Details

File #: 26-1219    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 6/12/2026 In control: City Council
On agenda: 7/27/2026 Final action:
Title: Consideration to approve a contract with Park Place San Antonio, TX in the total amount of $523,589.69 for the purchase and installation of playground equipment amenities for Noon Lions Park (5701 Gallagher Ave.) in the amount of $278,633.66 and Zacate Creek Poggenpohl Park (101 Poggenpohl St.) in the amount of $244,956.03 for the Parks & Recreation Department, utilizing the BuyBoard Cooperative Purchasing Program #781-25. All labor, materials, equipment, insurance, and bonds included in the total price. Funding for these projects is available in the 2025 Certificate of Obligations Bond.
Attachments: 1. 2026.03.05 LaredoPARKS_PROPOSAL_ (004)-pages-4, 2. 2026.03.05 LaredoPARKS_PROPOSAL_ (004)-pages-2-pages-1, 3. Quote - poggenpohl, 4. BuyBoard Contract #781-25 Park Place
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT

title

Consideration to approve a contract with Park Place San Antonio, TX in the total amount of $523,589.69 for the purchase and installation of playground equipment amenities for Noon Lions Park (5701 Gallagher Ave.) in the amount of $278,633.66 and Zacate Creek Poggenpohl Park (101 Poggenpohl St.) in the amount of $244,956.03 for the Parks & Recreation Department, utilizing the BuyBoard Cooperative Purchasing Program #781-25. All labor, materials, equipment, insurance, and bonds included in the total price. Funding for these projects is available in the 2025 Certificate of Obligations Bond.

 

body

PREVIOUS COUNCIL ACTION

None

 

BACKGROUND


Approved in the FY25-FY26 budget for the 2025 Certificate of Obligations, the playgrounds are prioritized in each district; selected and replaced by priority. Estimated completion time upon receipt of order is ninety to one hundred twenty working days.

1.)
                     Noon Lions Park (5701 Gallagher Ave.) in the amount of $278,633.66 (Dist. VII)

2.)
                     Zacate Creek Poggenpohl Park (101 Poggenpohl St.) in the amount of $244,956.03.(Dist.VIII)


Noon Lions Park

Description
                                                                                                                                                   QTY                     Unit Price                     Ext. Price

Demolition: remove/haul away existing playground equipment and pea gravel surfacing to appropriate depth
                                                                                       1                      $17,200.00                     $17,200.00

Shade Canopy: use existing shade canopy, remain in place
                     EXISTING                                          

Concrete Work: #3 rebar reinforced concrete slab 5” depth with control joints and base material underneath
                                                                                                                  
                                                                                       2462    $19.80
                     $48,747.60

Surfacing: rubber poured in place surfacing based on fall height of play equipment  

                                                                                       2462    $24.63
                     $60,639.06

Drainage: drain pipe to lateral sump                                1        $3,600.00    $3,600.00                                   

Temporary Fencing and Security: chain link perimeter fence; security on site during rubber surfacing
                                                                                         1        $4,480.00
                     $4,480.00

On-Site Storage: temporary storage container
                                             1                     $1,100.00                     $1,100.00

BuyBoard Discount (BuyBoard Contract #781-25)
                                                                  ($23,550.00)

Installation of equipment
                                                                                                                                                    $33,150.00

Freight
                                                                                                                                 $6,514.00

Grand Total                                                                                                    $278,633.66


Zacate Creek - Poggenpohl Park


Description
                                                                                                                                                   QTY                     Unit Price                     Ext. Price

Demolition: remove/haul away existing playground equipment and pea gravel surfacing to appropriate depth
                     
                                                                                         1
                     $12,400.00                     $12,400.00

Shade Canopy: USA Shade & Fabric Hip Structure 40x40 w/ 18’ eave height , includes engineered drawings
                                                                                                 $19,880.00    $19,880.00
                                          
Playground: Miracle Recreation Kids Choice #714-S728 Mega Tower Structure
                                                                                         1      $102,924.00  $102,924.00

Benches: 6’ long bench  MRSG303D                              4      $630.00         $2,520.00

Concrete Work: #3 rebar reinforced concrete slab 5” depth with control joints and base material underneath
                     
                                                                                        1761 $22.60
                     $39,798.60

Surfacing: rubber poured in place surfacing based on fall height of play equipment     

                                                                                        1661 $24.63
                     $40,910.43

Drainage: drain pipe to lateral sump                                1      $2,400.00      $2,400.00                                   

Temporary Fencing and Security: chain link perimeter fence; security on site during rubber surfacing
                                                                                         1       $3,100.00
                     $3,100.00

On-Site Storage: temporary storage container
                                             1                     $1,500.00                     $1,500.00

BuyBoard Discount (BuyBoard Contract #781-25)
                                                                  ($23,007.00)

Installation of equipment
                                                                                                                                                    $36,630.00

Freight
                                                                                                                                 $5,900.00

Grand Total                                                                                                    $244,956.03

 

COMMITTEE RECOMMENDATION

None

 

STAFF RECOMMENDATION

recommendation

Staff Recommends approval of this item.

end

Fiscal Impact

 

Fiscal Year:                                                                                                          2025/2026

Budgeted Y/N?:                                                                                    Yes

Source of Funds:                                                                                     2025 Certificate of Obligations

Account #:                                                                                                          478-3118-555-9301

Change Order: Exceeds 25% Y/N:                      Yes

 

FINANCIAL IMPACT:

Funding is available in account 478-3118-555-9301

PA2617 (PLAYGROUND-NOON LYON)                      $278,634.00

PA2622 (PLAYGROUND-ZACATE/POG)                     $244,957.00