Legislation Details

File #: 24-0170    Version: 1
Type: Consent Agenda Status: Tabled
File created: 12/28/2023 In control: City Council
On agenda: 1/22/2024 Final action: 1/22/2024
Title: Consideration for approval of Fasken Community Center Pool & Amenities Project, including the tree house and water feature project as complete, approval of change order No.3, a total decrease of $65,277.43 to balance quantities, release of retainage, and approval of final payment in the amount of $44,240.75 to Celso Gonzalez Construction, Inc., Mission, Texas. The final construction contract amount is $512,231.17. Funding is available in the Capital Improvement Fund and 2019 CO Bond.
Attachments: 1. Fasken - Change Order No. 3, 2. Fasken - Final Payment, 3. Fasken - Status Report December 2023

 

SUBJECT

title

 

Consideration for approval of Fasken Community Center Pool & Amenities Project, including the tree house and water feature project as complete, approval of change order No.3, a total decrease of $65,277.43 to balance quantities, release of retainage, and approval of final payment in the amount of $44,240.75 to Celso Gonzalez Construction, Inc., Mission, Texas. The final construction contract amount is $512,231.17. Funding is available in the Capital Improvement Fund and 2019 CO Bond.

 

body

PREVIOUS COUNCIL ACTION

 

On December 5, 2022, City Council approved change order No. 2, an increase of $30,000.00, and an increase of 206 calendar days for project completion to a construction contract with Celso Gonzalez Construction, Inc., Mission, Texas., for the Fasken Community Center Pool & Amenities Project including the tree house and water feature. In addition, the City of Laredo will assist Studio Cortes in providing in-kind services in the estimated amount of $20,000.00, for scaffolding, ready-mix concrete (3.5 cubic yards), concrete pump sprayer, workforce (2-3 staff members), and housing (3 months) to complete the project. Current total contract amount including this change order is $577,508.60, and contract time of 962 calendar days. Proposed commencement date is December 12, 2022, and estimated completion date is March 30, 2023. Funding is available in the 2014 CO Bond and 2016 CO Bond.

 

On May 2, 2022, City Council approved change order No. 1, an increase of $84,400.00, an increase of 360 calendar days due to delays and 126 calendar days for project completion of the tree house, re-assigned amounts from tree house site work and contingency allowance assigned towards completion of the water features to a construction contract with Celso Gonzalez Construction, Inc., Mission, Texas., for the Fasken Community Center Pool & Amenities Project. Current total contract amount including this change order No. 1 is $547,508.60, and contract time of 756 calendar days. Estimated commencement date is May 9, 2022 and estimated completion date is August 11, 2022.

 

On June 15, 2020, City Council approved to award a construction contract to the lowest responsible responsive bidder Celso Gonzalez Construction, Mission, Texas, in the amount of $463,108.60 (base bid minus alternate no. 2) with a construction contract time of two hundred seventy (270) calendar days.

 

BACKGROUND

 

This project consists of:

•    A kids tree house constructed of reinforced concrete by Studio Cortes; and

•    A "natural creek" like water feature;

 

Original Contract                                                                $463,108.60                     270 calendar days

Change Order No.1                                                               $84,400.00                     486 calendar days

Change Order No. 2                                          $30,000.00                     206 calendar days

Change Order No. 3                                                 ($ 65,277.43)

Final Construction Amount                                          $512,231.17 calendar days

 

COMMITTEE RECOMMENDATION

N/A

 

STAFF RECOMMENDATION

recommendation

Approval of this motion

end

Fiscal Impact

 

Fiscal Year:                                                                                                          2024

Budgeted Y/N?:                                                                                    Y

Source of Funds:                                                                                     CIP & 2019 CO BOND

Account #:                                                                                                          402-3118,402-4311,473-3118

Change Order: Exceeds 25% Y/N:                      N

 

FINANCIAL IMPACT:

Funding is available in the Capital Improvement Fud accounts 402-3118-555-9301, 402-4311-535-9301 and 473-3118-555-9301 with Project #D71830.