Legislation Details

File #: 26-1428    Version: 1
Type: Consent Agenda Status: Agenda Ready
File created: 7/16/2026 In control: City Council
On agenda: 8/3/2026 Final action:
Title: Consideration for approval of final payment for the construction of the 24-inch Water Transmission Main from Loop 20 Airport to Bustamante project, including all warranty certificates, release of retainage, and final payment in the amount of $336,940.08 to Southern Trenchless Solutions. The final construction contract amount of $6,738,801.50 and final contract time of 444 working days. Funding is available in the Waterworks Fund - 2020A Water Revenue Bond.
Attachments: 1. Southern Trenchless - Est#12 FINAL DRAFT - 24-inch HDPE Transmission Main Loop 20 Airport to Bustamante, 2. Pay App. Southern Trenchless - Est#12 FINAL DRAFT - 24-inch HDPE Transmission Main Loop 20 Airport to Bustamante
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

City of Laredo

Legislation Details

 

Meeting Date:                                                                                                                                                                         Consent Agenda

SUBJECT

title

Consideration for approval of final payment for the construction of the 24-inch Water Transmission Main from Loop 20 Airport to Bustamante project, including all warranty certificates, release of retainage, and final payment in the amount of $336,940.08 to Southern Trenchless Solutions. The final construction contract amount of $6,738,801.50 and final contract time of 444 working days. Funding is available in the Waterworks Fund - 2020A Water Revenue Bond.

 

body

VIVA LAREDO PLAN ALIGNMENT

Alignment Rating: Moderate

 

Supporting goal(s)/policy(ies):

Policy 6.5.7 Continue to implement the existing water conservation program

Policy 7.2.4 Increase access to safe water

 

Summary of alignment:

This agenda item update aligns with Viva Laredo’s Comprehensive Plan goals and policies related to efficient water utilization and sustainable development.

 

PREVIOUS COUNCIL ACTION

On March 21, 2022 council approved the construction contract to Southern Trenchless Solutions of La Feria, Texas in the amount of $5,773,625.00 with a contract time of 250 working days.
On July 22, 2024 council approved change order #1 in the amount of $716,865.36 with zero additional working days.
On March 07, 2025 council approved change order #2 in the amount of $231,311.14 with 50 additional working days.
On February 17, 2026 council approved change order #3 in the amount of $17,000 with 144 additional working days.

BACKGROUND

It is recommended to accept the 24-inch Water Transmission Main from Loop 20 Airport to Bustamante project as complete.

 

Contract

Amount

Working Days

Original Contract:

$ 5,773,625.00

250

Change Order # 1:

$    716,865.36

0

Change Order #2

$    231,311.14

50

Change Order #3

$      17,000.00

144

Total:

$ 6,738,801.50

444

 

COMMITTEE RECOMMENDATION

None.

 

STAFF RECOMMENDATION

recommendation

Approve this motion.

end

FISCAL IMPACT

Fiscal Year:                                                                                                          2026

Budgeted (Y/N):                                                                                    Y

Source of Funds:                                                                                     2020A Water Revenue Bond

Account #:                                                                                                          557-0000-206-0100

Change Order (Exceeds 25% Y/N):                      N

 

FINANCIAL IMPACT:

Funding is available in the 2020A Water Revenue Bond Retainage Account #557-0000-206-0100, Project ID: WP2201 with PO#361835.