Consideration to award a professional services contract to Crane Engineering, Laredo, Texas in the amount not to exceed $452,708.00 for FY25-ENG-37 Buena Vista Right of Way Dedication Plat Project for preliminary and final platting, design, TxDOT permitting, and construction phase services. Funding is available in the 2025 Tax Note Fund.
body
PREVIOUS COUNCIL ACTION
On October 6, 2025, City Council approved the selection of the top ranked consultant for the RFQ FY25-ENG-37 Buena Vista ROW Dedication Plat Project; and authorization to negotiate a professional services contract. A total of (3) firms responded to the request for qualifications Thursday, September 4, 2025. The committee recommends the selection of Crane Engineering.
BACKGROUND
Crane Engineering proposes to provide preliminary and final platting, design, TxDOTpermitting, and construction phase services for the Buena Vista street improvements project including geotechnical and environmental studies to comply with City OSS requirements.
VIVA LAREDO PLAN ALIGNMENT
Alignment Rating: Strong
Supporting goal(s)/policy(ies):
Policy 6.5.1 - Improve the safety, efficiency, and connectivity of the transportation network for all users.
Policy 6.6.2 - Require new and improved roadways to meet adopted city standards and coordinate with state and regional transportation agencies.
Policy 6.7.1 - Ensure that transportation infrastructure investments support planned growth areas and economic activity.
Summary of alignment:
The Buena Vista Right-of-Way Dedication Plat Project demonstrates strong alignment with the Viva Laredo Comprehensive Plan by directly implementing verbatim transportation and land use policies related to roadway standards, connectivity, interagency coordination, and infrastructure support for growth areas.
The agenda item advances mobility, economic development, and orderly growth by preparing critical right-of-way and roadway infrastructure in coordination with TxDOT and City standards. The scope of work-platting, design, permitting, and construction phase services-reflects a direct and intentional execution of adopted comprehensive planning policies, justifying a Strong alignment determination.
COMMITTEE RECOMMENDATION
N/A
STAFF RECOMMENDATION
recommendation
Approval of this motion.
end

Fiscal Impact
Fiscal Year: 2026
Budgeted Y/N?: Y
Source of Funds: 2025 Tax Note Fund
Account #: 479-2210-515-9301
Change Order: Exceeds 25% Y/N: N/A
FINANCIAL IMPACT:
Funding is available in the 2025 Tax Note Funds.
Account #479-2210-515-9301
Project #SP2601