Consideration to award a construction contract RFB 2026-079 to the lowest responsible, responsive bidder Trillium, LLC., DBA Cobalt Construction, Laredo, Texas in the amount not to exceed $4,502,258.00 for the construction of a Northside Materials Canopy and site improvements project for the Utilities Department. The estimated completion time is 210 working days. Funding is available in the Waterworks Fund-2022 Water Revenue Bond.
body
VIVA LAREDO PLAN ALIGNMENT
Alignment Rating: High
Supporting goal(s)/policy(ies): Supports the City’s goals
Summary of alignment:
PREVIOUS COUNCIL ACTION:
None
BACKGROUND
The City received three (3) bids through Cit-E-Bid for furnishing all the necessary materials, machinery, equipment, labor, superintendence and all other services and appurtenances required for the construction of a Northside materials canopy and site improvements project for the Utilities Department. The estimated completion time for this project is 210 working days. This contract shall be the responsibility of and administered between the vendor and the Utilities Department.
Summary:
Vendor: Project Total
Trillium, LLC., dba Cobalt Construction $4,502,258.00
Midas Contractors LLC $5,416,000.00
360 General Contractor Inc. $5,947,064.26
COMMITTEE RECOMMENDATION
None.
STAFF RECOMMENDATION
recommendation
Approve this motion.
end

Fiscal Impact
Fiscal Year: 2027
Budgeted Y/N?: Y
Source of Funds: 2022 Water Revenue Bond WP2310
Account #: 557-9879-535-9301
Change Order: Exceeds 25% Y/N: N/A
FINANCIAL IMPACT:
Funding is available in the 2022 Water Revenue Bond Project WP2310
.